Weekend update 1-19-15

Well it was another fun weekend around Gun Lab. This was the list I worked out during the week to be completed this weekend.

The 4″ conduit was run around the wood shop as well as the rest of the 2″ and 1″ and we buried it in preparation for the next phase.

[…]

Making the VG1-5 strengthening plates

In this post we are going to take you through the steps necessary to make the strengthening plates for the side of the VG1-5 receiver. In the first couple of rifles that we made we bent the plates on my finger brake.

This was not a plan for doing over 200 of them. The time […]

Weekend Update 12-29

Well this was a moving Saturday. I needed space in the fab shop and after looking at the deep hole drilling project for the last 10 years I figured it was time to move on. So with that being said it was time to move the big old lathe to the scrap yard. The first […]

Weekend update 12-14

Well another fun filled weekend has come and gone. A variety of projects were tackled and some minor accomplishment was achieved. The hole in the wood shop wall was filled in and sheet rocked over. Next weekend I will complete it and get it painted.

I have started moving equipment around in the fab shop […]

Weekend Update 11-24

Well as usual it has been a busy weekend around Gun Lab. More parts have been made for the VG1-5, coming soon in a post. The big project was the water system. The pressure pump took a crap. It just turn the pump room into a swamp and need to be fixed in a bad […]

Weekend update 11-10

It was a productive weekend as weekends go. The holes were drill into the side or the forging press I-beam to support the fluting machine. Here are a few pictures and a quick video of the process.

Moving the back plate over was no big deal, once in the fab shop it was loaded on […]

Weekend update 11-3

A number of items were worked on this weekend. Another section of the fab shop ceiling was completed as well as the out side cover for my forge exhaust.

Then it back at the fluting machine back plate.

The last item worked on was the stocks for the VG1-5. The have been […]

Tuesday shop pictures

What a shop to work in. And to think that the people that work in my shop complain about the working conditions.

I just don’t want to hear about the benches not being the right height or that we need a new cnc machine.

[…]

Monday update 9-29

The 1″ steel plate that we cut up last weekend has been cut down to size and then sized in the HAAS to actual specs.

This is all that is that is remaining of the steel sheet that we started with.

All of this material will be used on the fluting machine.This is what […]

Monday update 9-22

Well the fab shop new addition is now framed up and ready for a concrete pour. With any luck I will have the concrete completed in October.

This weekend is also honey-do weekend as well. The tile needed to put down in the hallway and bathroom and the new lighting installed. This […]